Lancashire Combined Fire Authority
Resources Committee
Meeting to be held 27 November 2024
(Appendices 1, 2 and 3 refer)
Contact for further information:
Steven Brown - Director of Corporate Services – Telephone Number 01772 826804
Executive SummaryThe report sets out the current budget position in respect of the 2024/25 revenue and capital budgets. RecommendationThe Committee is asked to: · note and endorse the financial position; and · approve additional slippage in the capital programme of £2.53m to 2025/26.
|
Information
Revenue Budget
In February 2024 the Combined Fire Authority agreed the Service’s 2024/25 revenue budget at £75.155m. This Financial Monitoring report is for the six-month period to the end of September 2024. The forecast outturn is £75.051m, which is a small underspend of (£0.103m). Of the forecast underspend, (£0.135m) relates to non-pay costs, and £0.032m to pay costs.
The year-to-date and forecast positions within all departmental budgets are set out in Appendix 1, with the major variances of note shown separately in the table overleaf.
Area |
Year to Date Variance
£m |
Reason |
Forecast Outturn Variance £m |
Reason |
Service Delivery - Pay |
0.181 |
The grey book pay award of 4% has been agreed and is effective from July 2024. This is 1% higher that our budgeted assumptions and accounts for majority of the overspend. |
0.653 |
The effect of higher than budgeted pay award results in a forecast cost pressure of £0.400m. Additional overtime costs have been incurred over the summer which has increased the forecast by £0.194m. |
Prevention and Protection - Pay |
(0.248) |
The year-to-date underspend is due to vacancies within the department. |
(0.415) |
Several vacant posts exist in the current staffing establishment for which recruitment and reorganisation is planned. It is anticipated that three posts will be recruited to in year, with a number of vacancies to persist for the duration of the financial year. |
Bank Interest |
(0.100) |
More interest has been earned on balances invested because of higher balances invested, due to slippage on the capital programme, and higher than budgeted interest rates. Interest earned on the Home Office pension grant received ahead of Matthews two and McCloud remedy has been assumed to be transferred to a reserve if required to be repaid. |
(0.200) |
The forecast reflects the full year effect of higher than budgeted interest rates and higher balances invested due to slippage in the capital programme. |
Fleet |
(0.086) |
Vehicle Repair and Maintenance (R&M) costs in the year to date are lower than budget to date. |
0.107 |
There is a small overspend forecast on R&M costs based on historic spending patterns. |
Occupational Health – Medical fees |
0.043 |
Staff medical fees are higher than budgeted due to the requirement for mandatory three-year screenings, recruitment screenings and referrals. The cost of providers remains high with few options between providers. |
0.114 |
Costs are anticipated to increase in the latter part of the year due to both On Call and Wholetime recruitment courses planned. |
(0.428) |
Programmed revenue maintenance costs have been delayed and is now expected to fall in the latter half of the financial year. Utilities expenditure has also been less than budgeted in the year to date. |
(0.331) |
The current outturn forecast currently assumes that property works will be undertaken as planned later in the year. Utility costs are currently forecast to underspend by (£0.400m) due to lower than budgeted usage and rates. |
Future Pressures
Pay award: Green book pay award negotiations concluded in late October. The national employers and trade unions agreed a pay award of £1,290 per annum (pro-rata for part-timers) on pay points 2 to 43, and an increase of 2.5% on locally determined pay points above 43. This will be paid in November and backdated to 1 April 2024. Current pay projections use the 3% budgeted rate. The revised forecast to include the new pay rate is not expected to change significantly.
Superannuation: The employer’s contribution rate to the 2015 Firefighters’ pension scheme as determined by the scheme actuary has been increased from 28.8% to 37.6%. Additional £2.5m grant funding has been received and added to the budget to offset this pressure, however, funding for 2025/26 is unknown at this stage.
Savings Targets
A reduction in the Contribution to Capital of £1.5m was agreed in the medium-term Financial Strategy resulting in a revenue contribution in 2024/25 of £2.5m. The budget has been reduced to this effect.
General Fund
The year end forecasted general fund position is summarised below:
|
£'m |
Opening balance of LFRS general fund |
(4.987) |
Forecast revenue underspend |
(0.103) |
Forecast closing balance of general fund |
(5.090) |
Note following the final outturn and audit of the financial statements, the opening general fund balance was updated from £4.918m to £4.987m.
Capital Budget
The revised Capital Programme for 2024/25 approved by the Resources Committee is £12m. To date £1.652m has been spent predominantly on fleet and operational equipment. A summary of the programme is set out in the table below and in more detail in Appendix 2.
Area |
Budgeted Items |
Budget (£m) |
Year to Date (£m) |
Slippage 2025/26 (£m) |
Operational Vehicles
|
The budget includes costs of two water towers, two climate change vehicles, three pumping appliances, a prime mover an aerial ladder appliance. All vehicles are on target to be delivered in 2024/25 with the exception of: · Pumping appliances are in the procurement process. · Aerial ladder appliance – delivery due early April 2025. · Large climate change vehicle in the procurement process and the small one at specification stage. |
2.943 |
0.446 |
1.501 |
Other vehicles
|
This budget allows for the replacement of various operational support vehicles including several cars, vans and a beavertail lorry. A few vehicles have been delayed to 2025/26: · Four Toyota Rav4 and two small vans are on order, however delivery expected early 2025/26. · Two double cab vans are in the procurement process. · Two rescue team vans have slipped due to delivery and conversion lead times. |
0.948 |
0.176 |
0.407 |
Operational Equipment
|
This budget allows for operational equipment purchases including CCTV cameras for appliances, body armour, and road traffic collision equipment. To date the following slippage includes: · Body Armour – the trial period has been completed and procurement process underway. · Flow meters and hose reel are on trial in Blackpool. It is anticipated there will be an additional budget requirement. · Breathing apparatus compressor is on order with an early 2025/26 lead time. |
1.846 |
0.812 |
0.470 |
Building Modifications
|
This budget includes the continued programme of Drill Tower Replacements, Blackpool facilities upgrade and budget for the initial works to support the upgrade to Preston station. Slippage to date has been identified as follows: · The enhancement of facilities at Blackpool (W30) has incurred some initial costs however will see final completion in 2025/26. · Most Drill Tower replacement works have slipped due to unsuccessful award of the contract. · Wylfra training props programme is due to start on site April 2024. · Options appraisal is underway for suitable land acquisition. · Estates improvements will continue into 2025/26. |
3.639 |
0.125 |
2.573 |
IT systems
|
This budget includes various projects including upgraded Firewalls, network upgrades and replacement of pooled PPE and stock management systems. Several IT system projects have been identified as likely to slip into 2025/26; the replacement systems for the management of stock, assets and pooled PPE, public switched telephone network. Existing contracts have been extended. The incident ground radios project has also slipped to next year due to other interdependencies with the breathing apparatus project. |
2.593 |
0.093 |
0.974 |
Potential Financial Risks
There are several potential scenarios that have not been reflected in this monitoring report that, if they materialise, may give rise to an increase in revenue and capital expenditure. To provide some information about potential significant financial risks these have been quantified to provide an estimated worst case scenario, these are set out in Appendix 3. Taking all these risks overall and adjusted for the remainder of the year, a potential worst-case scenario would impact the Revenue Budget and Capital Budget accordingly:
£m |
Worst Case |
Revenue Budget - unbudgeted costs |
3.25 |
Capital Budget – Additional Expenditure |
0.65 |
The potential worst-case scenario could be funded from available budgets but would reduce the general fund balance to below the minimum acceptable level agreed by the CFA.
Financial Implications
As outlined in the report
Legal Implications
None
Business Risk Implications
None
Environmental Impact
None
Equality and Diversity Implications
None
Human Resource Implications
None
Local Government (Access to Information) Act 1985
List of background papers
Paper:
Date:
Contact:
Reason for inclusion in Part 2 if appropriate: N/a
Appendix 1
Appendix 2
Capital Budget Monitoring as at 30th Sept 2024 |
||||||||||||||
|
||||||||||||||
CAPITAL BUDGET 2024/25 |
Revised Programme |
Actual as at 30th Sept 2024 |
Projected Year End Outturn |
Projected slippage as at 30th Sept 2024 |
Estimated final cost |
Over/ (Under) Spend |
||||||||
|
m |
m |
m |
m |
m |
m |
||||||||
Vehicles |
|
|
|
|
|
|||||||||
Operational Vehicles |
2.943 |
0.446 |
1.436 |
-1.501 |
2.937 |
-0.006 |
||||||||
Support Vehicles |
0.948 |
0.176 |
0.529 |
-0.407 |
0.936 |
-0.012 |
||||||||
|
3.891 |
0.622 |
1.965 |
-1.908 |
3.873 |
-0.018 |
||||||||
Operational Equipment |
|
|
|
|
|
|||||||||
Operational Equipment |
1.846 |
0.812 |
1.359 |
-0.470 |
1.829 |
-0.017 |
||||||||
|
1.846 |
0.812 |
1.359 |
-0.470 |
1.829 |
-0.017 |
||||||||
Buildings Modifications |
|
|
|
|
|
|||||||||
Update Preston Facilities |
0.500 |
0.015 |
0.250 |
-0.250 |
0.500 |
0.000 |
||||||||
Development & Land Acquisition |
0.340 |
- |
- |
-0.340 |
0.340 |
0.000 |
||||||||
Blackpool Dormitory |
0.834 |
0.022 |
0.434 |
-0.400 |
0.834 |
0.000 |
||||||||
Drill tower replacements |
1.208 |
0.074 |
0.125 |
-1.083 |
1.208 |
0.000 |
||||||||
Wylfa Prop |
0.125 |
- |
0.025 |
-0.100 |
0.125 |
0.000 |
||||||||
Estate Improvement Provision |
0.632 |
0.014 |
0.232 |
-0.400 |
0.632 |
0.000 |
||||||||
|
3.639 |
0.125 |
1.066 |
-2.573 |
3.639 |
0.000 |
||||||||
ICT |
|
|
|
|
|
|||||||||
IT Systems |
2.593 |
0.093 |
1.391 |
-0.974 |
2.365 |
-0.228 |
||||||||
|
2.593 |
0.093 |
1.391 |
-0.974 |
2.365 |
-0.228 |
||||||||
|
|
|
|
|
|
|||||||||
Total Capital Requirement |
11.969 |
1.652 |
5.781 |
-5.925 |
11.706 |
-0.263 |
||||||||
|
|
|
|
|
||||||||||
Funding |
|
|
|
|
||||||||||
Capital Grant |
- |
- |
- |
0.000 |
0.000 |
0.000 |
||||||||
Borrowing |
- |
- |
- |
0.000 |
0.000 |
0.000 |
||||||||
Revenue Contributions |
2.500 |
1.652 |
2.500 |
0.000 |
2.500 |
0.000 |
||||||||
Earmarked Reserves |
- |
- |
- |
0.000 |
0.000 |
0.000 |
||||||||
Capital Reserves |
9.469 |
- |
3.281 |
-5.925 |
9.206 |
-0.263 |
||||||||
Capital Receipts |
- |
- |
- |
0.000 |
0.000 |
0.000 |
||||||||
Total Capital Funding |
11.969 |
1.652 |
5.781 |
-5.925 |
11.706 |
-0.263 |
||||||||
|
|
|
||||||||||||
Fleet |
3.891 |
0.622 |
1.965 |
-1.908 |
3.873 |
-0.018 |
||||||||
Equipment |
1.846 |
0.812 |
1.359 |
-0.470 |
1.829 |
-0.017 |
||||||||
Property |
3.639 |
0.125 |
1.066 |
-2.573 |
3.639 |
0.000 |
||||||||
ICT |
2.593 |
0.093 |
1.391 |
-0.974 |
2.365 |
-0.228 |
||||||||
|
11.969 |
1.652 |
5.781 |
-5.925 |
11.706 |
-0.263 |
Appendix 3
Potential significant risks have been quantified to provide an estimated best case and worst case scenario for each risk.
|
Rev / Cap |
Worst Case (Full Year) £m |
Industrial Action (Risk 1a) – Costs based on reported figures from other fire authorities adjusted for inflation and size of authority. |
Rev |
2.5 |
Pandemic (Risk 1d) – Based on direct costs of COVID19, this was funded but this scenario assumes no funding provided. |
Rev |
1.3 |
Overspending and future financial pressures on MTFS due to increase in costs of goods and services and pay (Risk 2b) – based on highest one year CPI increase experienced of 13.5%. |
Rev |
2.0 |
As above. |
Cap |
1.3 |
Loss of Utilities (Risk 3) and ICT (Risk 4) – Includes additional repair costs, overtime, hire costs etc. |
Rev |
0.2 |
Operational Event (Risk 11) – large scale incidents and events can be significant however there are funding mechanisms such as Bellwin in place. This cost assumes a prolonged period of overtime that would not be met from national funding schemes. |
Rev |
0.5 |
Revenue Total |
|
6.5 |
Capital Total |
|
1.3 |